April 15, 2025
Progress at Mont Reve is powering ahead below the surface.
Lateral support and earthworks are well underway, with the team now working at Stage 2 of excavation. All piles have been successfully installed—a significant structural milestone—and over 100 of the planned 228 anchors are already in place.
Earthworks have reached 8.5 metres below ground level, with an estimated 3 to 5 metres remaining before hitting the expected rock levels. Nail installation will begin once we reach that depth.
Momentum is strong on site as we continue laying the foundation for something remarkable.